A PEB quotation provides a detailed breakdown of the costs involved in designing, manufacturing, supplying, and installing a Pre-Engineered Building. When comparing offers from Delhi suppliers, look beyond the total price. Evaluate material quality, steel specifications, design standards, transportation, installation charges, delivery timelines, and warranty terms to make an informed decision.
Published November 13, 2026
Quick Answer
A proper PEB quotation lists the building size and design basis, steel weight and grades, roof and wall cladding, accessories, painting or coating, transport, erection, taxes and payment terms, and states clearly what is not included. To compare offers fairly, put each quotation against the same specification and scope, then compare line by line instead of looking only at the total.
Why Two PEB Quotes Rarely Look Alike
You ask three suppliers for a price on the same shed, and the numbers come back far apart. That gap usually does not mean one supplier is cheaper or greedier. It means the quotations cover different things: different steel weights, thinner sheets, no insulation, no erection, or civil work left out.
Whether you are speaking to PEB manufacturers in Delhi or reviewing the top PEB supplier in Delhi on your shortlist, the only reliable way to choose is to read the quotation as a scope document, not a price tag. This guide shows what a complete quotation should contain, what often goes missing, and how to compare offers side by side. It is written by Kaizen PreFab, a team that works on pre-engineered buildings across Delhi NCR.
What a PEB Quotation Should Include
A complete quotation reads like a short specification. Use this table to check that each item is present and clearly described.
Item
What to look for
Building details
Length, width, eave height, roof slope, bay spacing and the number of buildings
Design basis
Design codes followed, wind and seismic assumptions, roof live load, crane or mezzanine loads
Primary framing
Steel grade, member type and total steel weight or tonnage
Secondary members
Purlins, girts, bracing and their grades
Roof and wall sheeting
Sheet thickness, coating type and colour, profile and warranty
Insulation
Type, thickness and where it is applied
Accessories
Skylights, ventilators, gutters, downspouts, louvres and flashings
Doors and openings
Rolling shutters, sliding doors, windows, with sizes and quantity
Painting and coating
Surface preparation, primer and finish coats, with thickness
Anchor bolts
Included or not, and who supplies the layout drawings
Transport
Delivery to your site included or charged separately
Erection
Supervision only, or full labour, tools and cranes
Drawings and approvals
Structural drawings and calculations provided for your approvals
Taxes and payment terms
GST, advance, milestone payments and validity of the offer
Delivery schedule
Dates for drawings, dispatch and completion
Warranty
What is covered, for how long and under what conditions
What Is Often Left Out or Priced Separately
The cheapest quotation often becomes the most expensive once the missing items surface. Check whether these are included, excluded or quoted as extras:
Civil work: Foundations, plinth beams, flooring and retaining walls are usually outside the PEB scope.
Anchor bolts and embedded parts: Some suppliers provide only the drawings.
Insulation and ventilation: Often optional, even though they matter in Delhi NCR summers.
Crane, mezzanine and equipment loads: If not stated in the design basis, they may not be covered.
Erection equipment:Cranes, scaffolding and power at site may be your responsibility.
Transport and unloading: Distance, vehicle type and unloading help can add to the cost.
Statutory work: Fire fighting, electrical work, plumbing and approvals are rarely part of the structure price.
Taxes: Confirm whether the quoted figure includes GST or adds it later.
For every item, ask one question: who does it, and at whose cost? A quotation that answers this clearly is far more trustworthy than a short one with a low total.
How to Compare PEB Offers Line by Line
Follow these steps to turn different-looking quotations into a fair comparison.
Give every supplier the same brief. Share the same drawings or a written specification, so all quotes start from identical requirements.
Compare steel weight. Ask each supplier for total tonnage. A much lower weight for the same building may mean lighter members or a different design basis, so ask why.
Compare sheeting and coating. Check thickness, coating specification and warranty. Small differences here change both cost and lifespan.
Match the scope. List inclusions and exclusions side by side: civil work, anchor bolts, insulation, transport, erection and approvals.
Normalise the price. Add the cost of items one supplier excludes to the others' totals, so every figure covers the same scope.
Check the schedule and payment terms. A faster delivery date or a smaller advance is worth money, but only if it is written in the offer.
Compare the people behind the offer. Review fabrication facility, past projects nearby and after-sales support.
Red Flags in a PEB Quotation
A single lump-sum figure with no breakdown of steel, sheeting, erection or taxes.
No steel weight or grade stated.
Vague words such as "as per standard" or "as required" instead of thickness, grade and quantity.
Exclusions hidden in small print or mentioned only verbally.
A price far below the others with no explanation for the difference.
No design basis, with no mention of wind, seismic or crane loads.
Large advance payments with no link to design or dispatch milestones.
No offer validity date, which leaves room for later price changes.
Unwillingness to show a factory or completed projects.
A single red flag is a reason to ask questions, not always to walk away. A pattern of them is a reason to look elsewhere.
Questions to Ask Before You Accept
When you are choosing between PEB manufacturers in Gurugram and other NCR suppliers, these questions make differences visible quickly:
Who prepared the structural design, and can we see the design basis?
What is the total steel weight, and which grades are used?
What exactly is excluded from this price?
Who is responsible for foundations, anchor bolts and their alignment?
Is erection done by your own team, and does the price include cranes and tools?
What is the delivery schedule, and what happens if it slips?
Can we visit your factory and a completed project near our site?
What does the warranty cover, and what support do we get after handover?
How are changes in scope priced after we sign?
A supplier who answers these in writing, without hesitation, is usually one who has thought the project through.
Conclusion
Kaizen PreFab prepares quotations that state the scope plainly, so you can compare them with any other offer. If you are looking for an industrial building manufacturer in Gurugram, or a PEB partner for Delhi, Manesar or Faridabad, share your plot size, intended use, loads and target date. We will help you define the specification first and then price it against that scope.
Have a quotation you want reviewed?Send it to Kaizen PreFab and we will walk through it line by line with you.